Design, Procurement, and Installation of Cathodic Protection System – 6” x 5km Ibeto Salt Gas Pipeline Project

Project Overview

JOCALSH INTERNATIONAL was commissioned by TGNL/Sellyfak to deliver a complete Cathodic Protection (CP) solution for the 6” x 5km Ibeto Salt gas pipeline. This project was initiated to prevent external corrosion of the newly installed pipeline infrastructure, which plays a vital role in the distribution of natural gas to industrial consumers in the Ibeto region.

The project scope involved a detailed design phase followed by the supply and installation of all CP system components. Our technical team ensured full system integration with robust field testing to validate compliance with client specifications and applicable international standards.


Services Provided

  • Route-specific CP system engineering and design

  • Procurement and delivery of CP equipment and accessories

  • Installation of sacrificial anodes, test stations, and bonding connections

  • Verification of electrical continuity and polarization effectiveness

  • Commissioning and system performance testing

  • Technical reporting and knowledge transfer to client teams